Capital Improvement Project Timeline
Jan. 19, 2021 - Public Information Meeting
Jan. 26, 2021 - Public Vote (passed with 86% approval)
Spring 2021 - Architects meet with key stakeholders in project to fine tune plans
September 2021 - January 2022 - Plans in State Education for Approval
February - April 2022 - Project Bidding and Awarding of Contracts
May 2022 - September 2023 - Construction Phase of Project